Project Update.

Welcome to the Westwood Project update portal.

Here you will find helpful up-to-date information regarding the construction on your stage.

Westwood Walk
Project Update July 2025

Welcome to our July Construction Update!

Melbourne’s Western Corridor is thriving as we embrace the cold winter blast in July. We warmly welcome all new residents who have recently settled or purchased within Westwood. As our neighbourhood continues to grow, we’re excited to share more updates—stay tuned for what’s ahead!

In the meantime, Plumpton Road (between Melton Highway and Tarletons Road) remains closed as upgrade works continue — including a new roundabout, pedestrian crossings, bike lanes, and wider footpaths.

These improvements will ease traffic flow and boost safety for Westwood residents and the wider Fraser Rise community. Completion is expected by the end of July 2025.

As construction of housing continues, please remind builders to manage waste responsibly. Report any illegal dumping to the council to help keep our community pristine.

Stage 15A: Due for Titles October 2025
Construction Commencement

With authority permissions now in place, our construction team commenced in May 2025.

Stage 21: Due for Title in May 2026
Plans & Permits

Council and other Authorities have confirmed the approvals and acceptance. The development team is currently conducting preparation works on-site to lay the groundwork for the stage which will commence in the coming weeks.

We look forward to sharing more updates with you soon!

Please Note: As previously advised, given the wet weather, all timeframes are provided as a guide and based on our best information at hand. Delays due to weather, site conditions, and authority output are being experienced and are outside of our control. We will continue to provide updates as new information arises.

Please find approximate timings in the table below of your stage:

Stage
Stage
Status
Title
1
Complete
Complete
2
Complete
Complete
3
Complete
Complete
4
Complete
Complete
5
Complete
Complete
6
Complete
Complete
7
Complete
Complete
8
Complete
Complete
9
Complete
Complete
10 & 11
Complete
Complete
12
Complete
Complete
13
Complete
Complete
14
Complete
Complete
14MD
Complete
Complete
Plan of Subdivision
Engineering Plan
15
Complete
Complete
16
Complete
Complete
17
Complete
Complete
18
Complete
Complete
19
Complete
Complete
20
Complete
Complete
15A
Construction Commencement
October 2025
Plan of Subdivision
Engineering Plan
21
Plans & Permits
May 2026
Plan of Subdivision
Engineering Plan

Westwood Place
Project Update July 2025

Welcome to our July Construction Update!

Winter is here now! And it hasn’t stopped delivery at Westwood Project. If anything, the school being delivered by the Department of Education is progressing to lock up stage and remains on track for 2026 opening.

In the meantime, Plumpton Road (between Melton Highway and Tarletons Road) remains closed as upgrade works continue — including a new roundabout, pedestrian crossings, bike lanes, and wider footpaths.

These improvements will ease traffic flow and boost safety for Westwood residents and the wider Fraser Rise community. Completion is expected by the end of July 2025.

Construction Progress

Works on Stages 7 and 9 are set to commence later this month.

Bulk earthworks and rockworks have been completed for the Waterway Drainage Reserve, with drainage works progressing well, marking the early delivery of key amenities.

We’re thrilled to see Westwood Place Vision taking shape and look forward to welcoming more residents soon.

Stage 3: Due for Title in July 2025
Statement Of Compliance

Currently progressing through the final approvals process, with the Statement of Compliance now imminent. This is a key milestone in preparation for title registration, keeping us on track for titles to be issued by July 2025.

Stage 4: Due for Title in November 2025
Sewer & Drainage

Sewer reticulation works have now been completed. The civil team is currently progressing with bulk earthworks within the temporary sediment basin, along with drainage and water reticulation works.

Please contact us if you have any questions or concerns.

Stage
Stage
Status
Title
1
Complete
Complete
2A
Complete
Complete
2B
Complete
Complete
8
Complete
Complete
3
Practical Completion Achieved
July 2025
Plan of Subdivision
Engineering Plan
4
Sewer & Drainage
November 2025
Plan of Subdivision
Engineering Plan

Register
Your Interest